Award

The construction contract for Riverside access works is awarded for CAD $3,700,000 excluding tax. It covers the baseline access-road and loading-bay work described in the award schedule.

Excluded from the award

Professional fees and owner costs are outside the contractor’s award. Their initial budget allowances are recorded in S01 allocation. The award is therefore $300,000 lower than the whole project budget without any missing-money inference.

Changes

The award note says a contract change needs a separately identified owner instruction and priced change. This note does not supply the full executed contract or delegation. It cannot establish whether every later instruction complied with those documents.

Every passage is part of this invented document. Exact passage links are supplied in the sample source index. The sample demonstrates source limits, not authenticity or admissibility of a real record.