- Stable source ID
- S04
- Illustrative record date
- 2025-11-30
- Record type and status
- Revised budget forecast. Invented revised spending plan
- Origin
- Created by Cyberdile for this educational sample. No real document was retrieved or redacted.
Forecast approval
The owner adopts a revised project budget of CAD $4,600,000 excluding tax. This resolution approves a revised spending plan. It expressly leaves item CH-02 subject to its separate owner instruction and pricing review.
Forecast allocation
| Category | Amount |
|---|---|
| Construction award plus registered CH-01 | $3,780,000 |
| Professional fees | $220,000 |
| Owner costs | $200,000 |
| Contingency | $280,000 |
| CH-02 drainage provision, not a priced instruction | $120,000 |
| Total | $4,600,000 |
Forecast is not payment
The contingency and drainage provision are allowances, not evidence that cash was spent. The revised budget does not certify completion, payment or a recoverable loss.