Illustrative record date
2025-11-30
Record type and status
Revised budget forecast. Invented revised spending plan
Origin
Created by Cyberdile for this educational sample. No real document was retrieved or redacted.

Forecast approval

The owner adopts a revised project budget of CAD $4,600,000 excluding tax. This resolution approves a revised spending plan. It expressly leaves item CH-02 subject to its separate owner instruction and pricing review.

Forecast allocation

Revised budget, CAD excluding tax
CategoryAmount
Construction award plus registered CH-01$3,780,000
Professional fees$220,000
Owner costs$200,000
Contingency$280,000
CH-02 drainage provision, not a priced instruction$120,000
Total$4,600,000

Forecast is not payment

The contingency and drainage provision are allowances, not evidence that cash was spent. The revised budget does not certify completion, payment or a recoverable loss.

Every passage is part of this invented document. Exact passage links are supplied in the sample source index. The sample demonstrates source limits, not authenticity or admissibility of a real record.